Delayed Commencement Is Not Work Suspension in South Korea — Supreme Court 2026Da200798
South Korea’s Supreme Court rules that delayed commencement caused by the contracting authority does not trigger liquidated damages under Clause 47(4). Learn what remedies Korean public construction contracts provide instead.