Construction Additional Payment Claim
Atlas Legal secured a KRW 53.3 million victory in an additional construction payment lawsuit involving excavation work at a construction site in Incheon. Case Overview Our client was a subcontractor who performed excavation and temporary facility work at a building construction site in Incheon. The excavation depth, originally contracted at 4 meters, was increased to […]
Deposit Withdrawal Rights Lawsuit Victory – 6-Creditor Competition Resolved
Attoreny’s of Atlas Legal successfully analyzed a complex 6-creditor garnishment competition in a KRW 20 billion construction project, securing approximately KRW 55 million in deposit withdrawal rights for a client undergoing bankruptcy proceedings. Case Overview A dispute arose over subcontract payment claims following the bankruptcy of the prime contractor in a KRW 20 billion waste-to-resource […]